So far in 2020, the northwest extension of Mack Hatcher Memorial Parkway has only made progress.
Crews have completed several aspects of the project, including beam and bridge work over both the Harpeth River and West Harpeth River. This has happened since the groundbreaking at the end of 2018.
“The first of several bridge deck pours was completed in April,” Tennessee Department of Transportation spokeswoman Kathryn Schulte said. “The next pour is scheduled to take place mid-late May. All beams have been set with the exception of the span over the West Harpeth River. This work is currently underway.”…